BYU-Idaho Center

Rexburg, Idaho

Record-Setting Long-Span Truss Erection by SME Steel

To keep the BYU–Idaho Center on schedule, the team reversed the steel erection sequence, so the roof could be set first and the building could be enclosed before heavy snowfall. As a result, the contractor gained a protected, temperature-controlled workspace earlier in the timeline.

Because of SME’s deep experience and trusted reputation, we were brought in during the design phase to help streamline detailing, fabrication, and field coordination. This early collaboration helped maintain the tight temperature-tolerance requirements needed for the trusses to fit with precision.

During installation, the 260-foot, 100-ton topping-out truss was carefully set between the 120-foot, 100-ton king truss and the precast walls with just six inches of clearance. In addition, SME fabricated and erected the King Truss—recognized as the largest truss ever erected in the State of Idaho. To complete the venue layout, the indoor track was raised 12 feet above the perimeter of ten full-size basketball courts, maximizing both space and functionality.

Project Details

04/01/2010

4,600 tons of steel

CLIENT

BYU-Idaho University

CONTRACTOR

Okland Construction

ARCHITECT

FFKR Architects

Project Gallery

steel building under construction
steel building under construction
steel building under construction
steel building under construction red sunset sky

Related Projects

2026-03-16T13:48:16-06:00

Henry Mayo Newhall Hospital

Henry Mayo Newhall Hospital Valencia, California Henry Mayo Newhall Hospital Patient Tower Expansion Henry Mayo Newhall Hospital is a new patient tower includes expanded laboratory services, materials management services, rooftop helipad with direct access to Emergency Department, large cafeteria, hotel-quality kitchen, central atrium, three medical-surgery floors, surgery

2026-03-16T13:50:22-06:00

BYU-Idaho Center

BYU-Idaho Center Rexburg, Idaho Record-Setting Long-Span Truss Erection by SME Steel To keep the BYU–Idaho Center on schedule, the team reversed the steel erection sequence, so the roof could be set first and the building could be enclosed before heavy snowfall. As a result, the contractor gained

2026-03-16T13:51:50-06:00

City College of San Francisco

City College of San Francisco Joint Use Facility Educational Facility Structural Steel Construction The City College of San Francisco Joint-Use Facility is comprised of a three-story building featuring classrooms, specialized laboratories, student development facilities, study space, and offices. The structure supports a green roof, central atrium, and

2026-03-16T13:53:44-06:00

St. Alphonsus Regional Medical Center

St. Alphonsus Regional Medical Center Boise, Idaho Structural Steel Delivered Without Interrupting Hospital Operations St. Alphonsus Regional Medical Center was constructed between two existing buildings and swallowed a working skybridge. This conventional braced structure was built in a horseshoe shape to allow continued access to the skybridge

2026-03-16T13:54:22-06:00

San Jose Regional Medical Center

San Jose Regional Medical Center San Jose, California Structural Steel Supporting a State-of-the-Art Hospital Expansion San Jose Regional Medical Center is a state-of-the-art, 138,000-square-foot patient tower and 24,000 square feet of renovations. The new expansion includes 32 medical/surgical beds, 32 post-partum beds, 26 bassinet newborn nursery beds,